Location : Thamar. Yemen
Start Date : 1998
Completion Date: 2000
Address :Thamar, Yemen
Total No. of staff-months: 50
Name of Associated consultants: A.karim Mohsen MCE, Cairo
Client : University of Thamar ,via A.karim Mohsen.
Project’s Brief
Start Date : 1998
Completion Date: 2000
Address :Thamar, Yemen
Total No. of staff-months: 50
Name of Associated consultants: A.karim Mohsen MCE, Cairo
Client : University of Thamar ,via A.karim Mohsen.
Project’s Brief
Library
- Multi uses building, it is built in three floors consists of:
- Three parts: Library, front yard, periodicals and cafeteria mass
- The main building included: Reading space, stacks space, administration, stores and the another accessories
- Advance modern Architectural building constructed using (R.F.) concrete structural system and cladding
by local off white and light brown stones in addition to aluminum and glass windows and curtain walls. - Equipped by very advance and up MEP systems including sounds, CCTV, intrusion, data and communication systems.
- The project located in the north – west of the university
- The approximate total built up area of 12,369 m
- Consist of two floors and basement in addition to outdoor plaza and open.
Science & Technology Collage
- The college building consists of the following:
- Three blocks, court yard, central services. and spin which is the main element of the project
- The academic activates included: lecture rooms and halls, library, laboratories, students facilities, staff and dean office.
- Advance modern Architectural building constructed using (R.F.) concrete structural system and cladding
by local off white and light brown stones in addition to aluminum and glass windows and curtain walls. - Equipped by very advance and up to date MEP systems including sounds, CCTV, intrusion, data and communication systems.
- The project located in the south east of Thamar university
- The total built up area of about 21,804 m2
- The project consists of four floors and one basement.
Agriculture Collage
- The college building consist of the following:
- Three blocks, court yard, central services. and spin which is the main element of the project
- The academic activates included: lecture rooms and halls, library, laboratories, students facilities, staff and dean office.
- Advance modern Architectural building constructed using (R.F.) concrete structural system and cladding by local off white and light brown stones in addition to aluminum and glass windows and curtain walls.
- Equipped by very advance and up to date MEP systems including sounds, CCTV, intrusion, data and communication systems.
- The project located in the south east of Thamar university
- The total built up area of about 21,804 m2
- The project consists of four floors and one basement.
Scope of Service
- Prepare conceptual and preliminary architectural designs.
- Prepare final detailed architectural, structural and MEP drawings and details.
- Prepare special and general technical specifications, bill of quantities and cost estimation.
- Prepare tender documents including the special, general condition and the form of contract.